Warehouse Conversion to Production Facility

Virginia Beach, Virginia

2018


Continued increases in market share prompted the conversion of a warehouse facility into a production facility. The requirements included 6 extrusion machines, 3 future extrusion machines, 5 injection molders, racking and associated equipment. The mechanical systems included rooftop air handling units with ductwork and diffusers, chilled water piping, condenser water piping, process condenser and chilled water piping, air compressors, air dryers, aluminum compressed air piping, chiller, cooling tower and DDC controls. The plumbing system included a new waste system trenched for the full length of the building, 3 new sinks and sprinkler system modifications. The total mechanical and plumbing budget was $1,500,000. Construction is scheduled to be completed in January 2019.

Address

401 Normandy Court
Virginia Beach, Virginia
23464

Contact

Email: ppropst@proengineering.design
Phone: 757-630-2863